| 1. Module Preparation |
| Task |
Description |
Date |
Operators |
Comments |
| 1.0 |
Record Module Number & Site |
16-11-00 |
V, R |
|
| 1.1 |
Set-up Module |
16-11-00 |
V, R |
|
| 1.2 |
Set-up Work Space and Supplies |
16-11-00 |
V, R |
|
| 1.3 |
QC0:
Initial Inspection |
16-11-00 |
R |
|
| Sub Item |
OK |
Not OK : List problems and
repairs |
| 1.3a) Residual Glue,
paint, contaminants |
OK |
|
| 1.3b) Spring Pins |
OK |
|
| 1.3c) Plate/Weld Bar Edges |
OK |
|
| 1.3d) Sub module Shims and
Spacing |
OK |
|
| 1.3e) Painted Surfaces |
OK |
|
| 1.3f) Slot Widths |
OK |
|
| 1.3g) Overall dimensions |
OK |
|
| 1.4 |
Clean and paint Module Surfaces |
16-11-00 |
V, R |
|
| 1.5 |
Close girder holes with aluminium tape |
16-11-00 |
R, V |
|
| 1.6 |
Install Fiber Fixation Rails
+ Pieces for Bundle Fiber Fixation |
17-11-00 |
P, R |
|
| 1.7 |
Record Aspirin Tube Batch # |
14-11-00 |
R |
D10.3: IF080900; D5.5: 4 units from
IF151100 and 4 units from IF080900; D7.5: IF080900; D14.5: 080900; D12:
IF151100 |
| 1.8 |
Install Aspirin Tubes and washers |
16-11-00 |
V, R |
|
| 1.9 |
Mark Cell Boundaries and
Label holes with cell numbers |
16-11-00 |
R,V |
| 2. Tile Installation |
| Task |
Description |
Date |
Operators |
Comments |
| 2.1 |
QC1a:
Tile Inspection |
17-11-00 |
P, R |
|
| Sub Item |
OK |
Not OK : List problems and
repairs |
| 2.1a) Tile Color |
OK |
There are important diferences
between the color of tiles of size 1, 2, 3, 4, 5, 6 and the tiles of size 7, 8, 9,10, 11 |
| 2.1b) Tile End Surfaces |
OK |
Tiles of size 7 were painted to
reduce luminosity. |
| 2.1c) Tile Wrappers |
OK |
|
| 2.2 |
Record Tile Batch and pack Numbers |
16-11-00 |
V, R |
|
| Tile Size |
Packs ID |
Comments |
| 1 |
647(19), 644, 648, 752, 645, 662,
664, 642(1) |
Packs ordered from End Plate to
ITC. The numbers between brackets are the number of tiles extracted from the pack written
just before. If there is not a bracked number after the pack number it means that 20 tiles
were extracted from that pack. |
| 2 |
26(7), 25, 34, 24, 43, 36, 169,
119(13) |
|
| 3 |
709(15), 710, 712, 711, 850, 856,
843, 855(5) |
|
| 4 |
478 (19), 75, 208, 83, 441, 527,
207, 210(1) |
|
| 5 |
514, 60, 33, 442, 432, 463, 389 |
|
| 6 |
70, 81, 72, 85, 79, 80, 71 |
|
| 7 |
142(14), 188, 187, 185, 143, 201,
163, 159(11); 1 special tile IF190900 |
|
| 8 |
549(3), 629, 16, 527, 594, 624,
593, 599, 598(1); 1 special tile IF190900 |
|
| 9 |
25 (13), 48, 8, 24, 9, 87, 617,
64(12); 1 special tile IF190900 |
|
| 10 |
194(16), 156, 154, 203, 212, 233,
282, 226; 1 special tile IF190900 |
|
| 11 |
475(5), 477, 498, 479, 124, 190,
177, 120, 181(12) |
|
| 2.4 |
Insert Tiles |
17-11-00 |
R, P |
|
| 2.5 |
QC1b:
Tile Inspection after insertion |
17-11-00 |
P, R |
|
| Sub Item |
OK |
Not OK : List problems and
repairs |
| 2.5a) Tile Sizes |
OK |
|
| 2.5b) Tile End Surfaces |
OK |
Air bubles in some tiles |
| 2.5c) Tile Wrappers |
OK |
|
| 2.6 |
Put Shims where it was needed |
15-11-00 |
R, V |
|
| 2.7 |
Install and close rods |
30-11-00 |
R,P |
| 5. Fiber Routing |
| Task |
Description |
Date |
Operators |
Comments |
| 5.1 |
Count fibers inside |
20-11-00 |
P, R |
|
| 5.2 |
Route Sub-bundles To Aspirin Tubes |
20-11-00 |
P, R |
|
| 5.3 |
Remove fibre separator strings |
30-11-00 |
P, R |
|
| 5.4 |
Remove one rod from each tile size |
|
|
The rods where not yet installed at this
point. |
| 5.5 |
Introduce the LED/light tubes |
20-11-00 |
P, L |
|
| 5.6 |
QC3:
Verify Fiber Routing |
20-11-00 |
P, L |
|
| Sub Item |
OK |
Not OK : List problems and
repairs |
| 5.6a) Routing mistakes |
OK |
|
| 5.6b) Bad tile/fibre coupling |
OK |
|
| 5.6c) Profiles coming out of
the grooves |
OK |
|
| 5.7 |
Register and secure Fibers in aspirine
tubes |
20-11-00 |
P, R |
|
| 5.8 |
QC4:
Fiber Registraton and Damage |
20-11-00 |
P, L |
|
| Item |
OK |
Not OK : List problems and
repairs |
| 5.8a) Stress Crazing |
OK |
A lot of fibers damaged |
| 5.8b) Cladding Damage |
OK |
|
| 5.8c) Fiber Curvature |
OK |
|
| 5.8d) Fibers outside girder |
OK |
|
| 5.9 |
Secure the sub-bundles with velcro straps
and adjust ends |
20-11-00 |
P, R |
|
| 5.10 |
Insert the dummy fibres |
20-11-00 |
P, R |
|
9. Install Source Tubes
(This task will be done at CERN for all modules.) |
| Task |
Description |
Date |
Operators |
Comments |
| 9.1 |
QC7a:
Check Source tube holes |
. |
. |
. |
| 9.2 |
Measure module length |
. |
. |
. |
| 9.3 |
Cut straight tubes |
. |
. |
. |
| 9.4 |
Prepare tube ends |
. |
. |
. |
| 9.5 |
Clean tubes |
. |
. |
. |
| 9.6 |
QC7b:Test with Dummy capsule |
. |
. |
. |
| Sub Item |
OK |
Not OK : List problems and
repairs |
| Straight Tubes |
. |
. |
| Bent Tubes |
. |
. |
| 9.7 |
Glue pairs of straight tubes to make 'U's |
. |
. |
. |
| 9.8 |
Passing test of 'U' s with dummy capsule |
. |
. |
. |
| 9.9 |
Insert 'U's |
. |
. |
. |
| 9.10 |
Glue the rest of bent tubes |
. |
. |
. |
| 9.11 |
Intermediate passing test of glued parts of
pipe system |
. |
. |
. |
| Sub Item |
OK |
Not OK : List problems and
repairs |
| 9.12 |
QC7a: Final passing test of pipe system with dummy capsule |
. |
. |
. |
| 9.13 |
QC7b: Final pressure test |
. |
. |
. |
| Sub Item |
OK |
Not OK : List problems and repairs |